Following operations are required to seek approval from Operations and Planning Department (OPD)
FPSO Operations include:
> FPSO under tow arrival and departure from Port
> Repair works at Anchorage
In your submission, you should include the draft Standard Operating Procedures (SOP) and any other relevant document related to the operation at E-mail pms@mpa.gov.sg. The information should include but not limited to the following details, where applicable;
Prior arrival / movement of FPSO
| 1. | a) Vessel particulars and description, height draft, length and any other peculiarity. |
| b) Activities to be carried out | |
| c) Safety plan | |
| d) Communication plan and contact numbers of the person in charge of the operations | |
| e) List and particulars of crafts involve including safety boat | |
| f) Contingency plan for emergency tug and pilot requirements | |
| g) Timeline for the activities to be carried out | |
| h) Details of operations / works required to be carried out | |
| 2. | Pre-operational meeting, together with other relevant parties (PSAM Pilots, Agents of vessels, Master / Superintendent of vessels etc) might be required, after consulting with MPA |
| 3. | Comply with Port Marine Circular No 27 of 1998 –Safety of Air Navigation. |
| 4. | Pre-operational meeting together with other relevant parties might be required, after consulting with MPA. |